Assessment 2 Deliverables

Change Report{:target="_blank"}
Implementation{:target="_blank"}
Testing{:target="_blank"}
Continuous Integration{:target="_blank"}

Updated Requirements{:target="_blank"}
Updated Architecture{:target="_blank"}
Updated Method Selection and Planning{:target="_blank"}
Updated Risk Assessment and Mitigation{:target="_blank"}

Source Code

Source Code{:target="_blank"}

Weekly Gantt Chart Snapshots

These are the weekly snapshots for our Gantt Chart, the more full a bar is, the more complete the task is.

02-05-22

We finished up the project and reviewed our work.

gantt chart for 02-05-22

25-04-22

We started finishing up on the code, and started focusing on the writeups more.

gantt chart for 25-04-22

18-04-22

Over the easter break we almost finished implementation and testing. We renamed the continuous integration section on the chart as it reflects better what we meant by it.

gantt chart for 18-04-22

14-03-22

We have finished developing the website so that it is easy to update throughout the project and have implemented github actions to run tests on the code.

gantt chart for 14-03-22

07-03-22

We have decided to increase website development due to unforseen issues with Jekyll themes.

gantt chart for 07-03-22

28-02-22

gantt chart for 28-02-22

21-02-22

gantt chart for 21-02-22

14-02-22

gantt chart for 14-02-22